Discovery Elementary Expansion/Remodel 1610
The addition of 6 new classrooms at Discovery Elementary School helped meet ISD's growth need. The project also included relocation of the Administration and Special Services areas, expanded the Commons and improved safety and security. The project was completed in September 2019.
Discovery Elementary School Remodel 1610
Original Project Estimate: |
$9,000,000 |
Estimated Final Project Cost: |
$14,557,927 |
Funding Source: |
2016 Bond |
Project Status: |
Complete |
Architect: |
Bassetti Architects |
Contractor: |
Kassel & Associates |
Estimated Completion: |
September 2019 |
Final Completion: | September 2019 |
Address: | 2300 - 228th Ave. SE, Sammamish |
Website: | Discovery Elementary School |