Gibson Ek High School 1205
Gibson Ek High School is the district's non-comprehensive high school that opened its doors in September 2016.
Gibson Ek High School is the district's non-comprehensive high school that opened its doors in September 2016. The project included reprogramming and relocating the district's non-comprehensive high school to 700/800 area of the former Issaquah Middle School site, enhancing the program and increasing space.
Gibson Ek High School 1205
Original Project Estimate: |
$3,925,000 |
|
---|---|---|
Current Project Budget: |
$6,448,635 |
|
Final Project Cost: | $6,448,635 | |
Funding Source: | 2012 Bond | |
Project Status: | Complete | |
Architect: | Cornerstone Architectural Group | |
Contractor: | Cornerstone General Construction | |
Estimated Completion: | September 2016 | |
Final Completion: | September 2016 |
Address: | 379 - 1st Place SE, Issaquah |
Website: | Gibson Ek High School |