Gibson Ek High School is the district's non-comprehensive high school that opened its doors in September 2016.

 

Gibson Ek High School is the district's non-comprehensive high school that opened its doors in September 2016. The project included reprogramming and relocating the district's non-comprehensive high school to 700/800 area of the former Issaquah Middle School site, enhancing the program and increasing space.

 

 

 

 

 

 

 

 

 

Gibson Ek High School 1205

  Original Project Estimate:                                        

$3,925,000

  Current Project Budget:

$6,448,635

  Final Project Cost: $6,448,635
  Funding Source: 2012 Bond
  Project Status: Complete                                     
  Architect: Cornerstone Architectural Group
  Contractor: Cornerstone General Construction                                                                      
  Estimated Completion: September 2016
  Final Completion: September 2016

 

Address:                                                                                       379 - 1st Place SE, Issaquah                                                                                 