Holly Street Creek Bank Repairs
In Spring 2020 the rising waters of Issaquah Creek eroded a portion of the creek bank and undermining of the parking lot at the Holly Street Campus site.
The Capital Projects Team started the very complex design and permitting for repair work within a salmon/fish bearing stream and approximately 1/2 mile downstream of a fish hatchery.
Due to permitting complexities the permitting process was split up into 2 parts; temporary and permanent. The temporary work was completed Spring 2021 and the permanent work was completed October 2022.
ISD is working with FEMA for reimbursement of costs related to the creek bank erosion repairs.
Project Information
Original Project Estimate: (2019) | $1,500,000 |
---|---|
Estimated Final Project Cost: (as of 11/22) | $1,800,000 |
Funding Source: | Levy 2022 |
Project Status: | Complete |
Architect: | Cornerstone Architectural Group |
Contractor: | Mike McClung Construction Co. |
Estimated Completion: | September 2022 |
Final Completion: | October 2022 |
Holly Street Creek Bank Repairs
Address: | 565 NW Holly Street, Issaquah, WA 98027 |
Website: | N/A |