Skip To Main Content

Search Panel

Schools Menu

Holly Street Creek Bank Repairs

In Spring 2020 the rising waters of Issaquah Creek eroded a portion of the creek bank and undermining of the parking lot at the Holly Street Campus site.

The Capital Projects Team started the very complex design and permitting for repair work within a salmon/fish bearing stream and approximately 1/2 mile downstream of a fish hatchery.

Due to permitting complexities the permitting process was split up into 2 parts; temporary and permanent.  The temporary work was completed Spring 2021 and the permanent work was completed October 2022.

ISD is working with FEMA for reimbursement of costs related to the creek bank erosion repairs.

 

Project Information

Original Project Estimate: (2019)                           $1,500,000                                                            
Estimated Final Project Cost: (as of 11/22) $1,800,000
Funding Source: Levy 2022
Project Status: Complete
Architect: Cornerstone Architectural Group
Contractor: Mike McClung Construction Co.
Estimated Completion: September 2022
Final Completion: October 2022

 

Holly Street Creek Bank Repairs

Address:                                                                     565 NW Holly Street, Issaquah, WA   98027
Website: N/A