The project includes improvements to the Holly Street Building (old Admin Bldg) to accommodate new ECAEP & ECE classrooms, the Child Find Program, a Health Room to serve the campus, among other amenities. The BASC Program will also be housed in this newly remodeled facility.
Holly Street Early Learning Center 2001
The Holly Street Early Learning Center project utilized the "old ISD Administration Building" and turned it into a premier early childhood learning center. The project included 2 new ECAEP classrooms, 2 new ECE classrooms, space for the Child Find Program, office space for Administrators, a Health Room, as well as improved BASC classrooms. The project was completed August 2022.
Holly Street Early Learning Center 2001
Original Project Estimate: | $1,500,000 |
---|---|
Estimated Final Project Cost: | $4,707,370 |
Funding Source: | Other Funding Source |
Project Status: | Complete |
Architect: | Cornerstone Architectural Group |
Contractor: | CDK Construction |
Estimated Completion: | Fall 2022 |
Final Completion: | Fall 2022 |