Issaquah High School Turf Replacements 1811

Issaquah HS Turf Replacement 1811

Original Project Estimate:                                           $1,300,000
Estimated Final Project Cost: (as of 11/22) $1,060,000
Funding Source: 2018 Levy
Project Status: Complete
Architect: DA Hogan & Associates
Contractor:                                      Coast to Coast Turf & Field Turf USA       
Estimated Completion: Fall 2023
Final Completion: Fall 2023

 

Address:                                                                             700 - 2nd Ave SE, Issaquah                       
Website:  https://issaquahhigh.isd411.org/