Issaquah Valley Elementary Expansion 1202

Issaquah Valley Elementary School Addition & Modernization 1202

Original Project Estimate:  $8,105,000
Current Project Budget: $8,354,599
Final Project Cost: $8,354,599
Funding Source: 2012 Bond
Project Status: Complete
Architect: Cornerstone Architectural Group                    
Contractor: Cornerstone General Contractors
Estimated Completion: September 2014
Final Completion: September 2014

 

Address:                                                                                     555 NW Holly Street, Issaquah         
Website:                                                                                      Issaquah Valley Elementary