Roof Repairs 1809

Roof Repairs - District Wide 1809

Original Project Estimate:                       $325,000
Final Project Cost:  $336,486
Funding Source: 2018 Levy
Project Status: Complete
Architect: N/A
Contractor:                                      N/A                                                       
Estimated Completion: July 2025
Final Completion: August 2025

 

Address:                                                                                           Various
Website:  N/A