Sunset Elementary Expansion 1613

Photo of the view between the commons and classrooms at Sunset Elementary

 

The Sunset Elementary School project included a new 2-story 6 classroom addition, expansion of the Multipurpose Room and a new Kitchen.  The project was completed September 2018.

Sunset Elementary School Remodel 1613

Original Project Estimate:   $7,000,000
Current Project Budget: $11,350,000
Final Project Cost: $11,346,349
Funding Source:

2016 Bond                       

Project Status:

Complete
Architect: Bassetti Architects
Contractor:          Cornerstone General Contractors    
Estimated Completion: September 2018
Final Completion: September 2018

 

Address:                                                                              4229 W. Lake Sammamish Pkwy SE, Bellevue  
Website:  Sunset Elementary School