Sunset Elementary Expansion 1613

The Sunset Elementary School project included a new 2-story 6 classroom addition, expansion of the Multipurpose Room and a new Kitchen. The project was completed September 2018.
Sunset Elementary School Remodel 1613
| Original Project Estimate: | $7,000,000 |
| Current Project Budget: | $11,350,000 |
| Final Project Cost: | $11,346,349 |
| Funding Source: |
2016 Bond |
|
Project Status: |
Complete |
| Architect: | Bassetti Architects |
| Contractor: | Cornerstone General Contractors |
| Estimated Completion: | September 2018 |
| Final Completion: | September 2018 |
| Address: | 4229 W. Lake Sammamish Pkwy SE, Bellevue |
| Website: | Sunset Elementary School |