Sunset Elementary Expansion 1613
The Sunset Elementary School project included a new 2-story 6 classroom addition, expansion of the Multipurpose Room and a new Kitchen. The project was completed September 2018.
Sunset Elementary School Remodel 1613
Original Project Estimate: | $7,000,000 |
Current Project Budget: | $11,350,000 |
Final Project Cost: | $11,346,349 |
Funding Source: |
2016 Bond |
Project Status: |
Complete |
Architect: | Bassetti Architects |
Contractor: | Cornerstone General Contractors |
Estimated Completion: | September 2018 |
Final Completion: | September 2018 |
Address: | 4229 W. Lake Sammamish Pkwy SE, Bellevue |
Website: | Sunset Elementary School |