Skip To Main Content

Search Panel

Schools Menu

Discovery Elementary Expansion/Remodel 1610

View of new classroom wing at Discovery

 

The addition of 6 new classrooms at Discovery Elementary School helped meet ISD's growth need.  The project also included relocation of the Administration and Special Services areas, expanded the Commons and improved safety and security.  The project was completed in September 2019.

Discovery Elementary School Remodel 1610

Original Project Estimate: 

$9,000,000                                                          

Estimated Final Project Cost:

$14,557,927

Funding Source:

2016 Bond

Project Status:

Complete

Architect:

Bassetti Architects

Contractor:

Kassel & Associates

Estimated Completion:

September 2019

Final Completion: September 2019

 

Address:                                               2300 - 228th Ave. SE, Sammamish
Website: Discovery Elementary School