• Project substantially complete and all areas are usable. Punchlist and commissioning well underway.
• Work to include; full HVAC replacement, fire sprinkler system replacement, enclosed walkway to the Gym area, exterior repaint and possibly some new limited room reconfigurations.
• Construction/installation of the new boiler room, new ball room, hydronic piping, VAV boxes, electrical underway. Six of the nine new HVAC units have been installed and are operational.